Construction Project Updates

2016 Roadway & Sewer Improvements in Rolling Acres Subdivision

Construction:  April 2016  – October 2016
Contractor:  Fabrizi Trucking & Paving Company
Amount:  $2,160,000.00

The work included in this project generally includes the replacement of 8” sanitary sewer main and laterals, storm sewer and lateral replacement, pavement removal and replacement, underdrain, concrete apron and sidewalk repairs, and lawn restoration on Laurel Drive, Concord Circle, Greenway Drive, Mortus Drive, and Sewer Easements in Rolling Acres Subdivision No. 4.   Public Meeting Notice   Construction Notice No.1


Sum-91-21.11 Darrow Road Widening from Post Road to Glenwood Drive

  

This project consists of a combination full depth reconstruction, widening and resurfacing of approximately 0.73 miles along SR91 (Darrow Road) from Post Road north through the Glenwood intersection.  The project includes curbs, sidewalks, and a modern roundabout at the SR91 and Glenwood Drive intersection. 

The Ohio Department of Transportation will be administering and performing all construction inspection for this project.  This project has been awarded to Karvo Paving Company for $4,745,581.52 and will continue through summer of 2016.

Tentative Schedule:

Engineering will continue to post a traffic advisory every two weeks for planned work.  Inclement weather will delay and extend schedule.

•   March 21st – Start excavation for widening on east side between Post and Glenwood  (3 months)

•   March 21st – continue utility work in the vicinity of the intersection SR91/Glenwood (Limit movement          onto EB Glenwood – WB traffic maintained)

•   Mid April – Temp Pavement SR91 at Glenwood Intersection

•   Late April close EB Glenwood mid June for pavement reconstruction of new intersection (Detour Posted     using Liberty- Post Road-Darrow)  Detour Map-Glenwood East 

•   Mid June close WB Glenwood Early Aug for pavement reconstruction of new intersection (Detour Posted     using Ravenna-Miktarian-Darrow)  Detour Map-Glenwood West

•   CLOSE BOTH LEGS OF GLENWOOD 15 days (Aug)

•   Mid June working on West Side SR91 between Post and Glenwood (3 months)

•   Install surface course of Asphalt, Pavement Markings and signage

•   Complete restoration/landscaping

•   Completion: November 2016


2016 City-Wide Tree Planting Program



Installation:  March 2016  – December 2016
Contractor:  Aaron Landscaping, Inc.
Amount:  $68,666.00

The 2016 City-Wide Tree Planting list has been compiled by the Engineering Department. 

If you have a tree lawn tree issue please contact the Service Department at 330.963.6212.

2017 Ravenna Rd Curb & Sidewalk Improvements Project



Proposed Construction:  March 2017 – May 2017
Bid Opened:  November 22, 2016 at 11:00 a.m.   
Engineer's Estimate:  $ 563,500.00

Work includes installing concrete sidewalk, concrete curb & gutter, storm sewer and appurtenances, curb drain, asphalt pavement removal and replacement, apron replacements, lawn restoration and miscellaneous work on south portion of Ravenna Road (southwest side) between Twinsburg RB Chamberlin Middle School and Gettysburg Drive and north portion of Ravenna Road between East Idlewood Drive and Heather Lane.  Work also includes Richner Court and Charles Court storm sewer improvements consisting of removal and replacement of storm structures and conduit including sidewalk, curb removal and replacement.

2017 Crestwood Drive Improvements Project


Proposed Construction:  March 2017 – September 2017
Bid Opened:  December 14, 2016 at 9:00 a.m.
Engineer's Estimate:  $1,238,000.00

The work included in this project generally includes replacement of existing sanitary service connections with new cleanouts, installation of 8” ductile iron water main, line valves, new hydrant assemblies and water service connections, storm sewer replacement and repairs, asphalt pavement, concrete apron an sidewalk repairs, and lawn restoration on Crestwood Drive.
COMMUNITY CONSTRUCTION

Corbett's Farm (Pulte Development)

Corbett Farm is a 94 lot single family residential development that started construction in October 2013. Corbett’s farm main entrance is located on Glenwood Drive with roads connecting to Meadowood,, Parkview, Corbett's Lane providing secondary access from both the Meadowood Subdivision and Chestnut Trails Subdivision.  All roadways have been installed and home building is occurring.  Pulte will complete sidewalk and grading along SR91/Glenwood Drive in spring of 2017. 

Fox Hollow Subdivision
Residential subdivision in R-5 district consisting of 24 lots. The Fox Hollow site is located adjacent to the Whitewood Apartments and accessed from Whitewood Parkway.  All roadways have been installed and Ryan Homes is currently building. 

Boulder Brook Subdivision
Planning Commission approved a preliminary plat for residential subdivision in R-5 district consisting of 27 lots. Boulder Brook is to be accessed from a cul-de-sac intersecting Darrow Road at Miktarian Memorial Parkway.  All roadways have been installed and Ryan Homes is currently building.

Shepard Preserve Subdivision
Residential subdivision consisting of 23 lots. Currently being reviewed by Planning Commission and if approved anticipated construction in 2017. Coblentz Homes is the builder.