Construction Project Updates

                                                                                                                                                

2024 Glenwood Drive Waterline CH08AA

Construction : May – August

Estimate: $585,650

This project received $285,000 in funded from the  Ohio Public Works Commission. The work includes the installation of 12” ductile iron water main, line valves, new hydrant assemblies and water service connections and pavement repair and restoration on Glenwood Drive between E. Idlewood and the Bridge over Tinkers Creek.  Glenwood Drive between E. Idlewood and Chestnut Trails/Gary Drive will be closed to thru traffic.  Residents located in the work zone will be able to access their properties from the west. Detour will be posted using Darrow Road to Officer Joshua T. Miktarian Parkway to Ravenna Road.

A Contract has been awarded by the City of Twinsburg to Northeast Ohio Trenching Services for the Glenwood Drive Waterline Replacement Project.

 The existing waterline will be replaced along Glenwood Drive from East Idlewood Drive to the bridge over Tinkers Creek.  The pavement and curb will be impacted on the north side of the road requiring the closure of the westbound lane for the duration of the project (eastbound traffic flow will be maintained for the majority of the project.  The existing waterline is in the center of the road prior to the bridge over Tinkers Creek.  When the work progresses to the bridge, the entire road will be closed for a connection to be made from the new water main to the existing waterline.

 A detour route has been included in this letter for your reference.

Maintenance of Traffic & Detour Route

 Work will begin the week of June 3rd.   Proposed work on this project is estimated to be completed by August 11th, weather permitting.

 You will have access to your driveway although there will be delays at times as work progresses. If you have any underground lawn sprinklers or pet fences in your tree lawn area please mark their location or let us know so the contractor can attempt to avoid damage to them.

 Temporary water shut offs will be required, and notice will be given by Cleveland Water Department and/or the contractor 24 hours in advance when feasible.

 Traffic will be maintained at all locations for residents, safety vehicles, school buses, mail delivery and rubbish pickup. Signs, barricades and cones will surround all work areas. Please drive slowly and safely through all construction areas. 

 The City of Twinsburg Engineering Department’s representative on site full time will be Patrick Jeffers or Joe Maniglia Office – 330.963.6247.  In case of an emergency beyond regular business hours, please call the Twinsburg Police Dispatch (Non-Emergency) @ 330.425.1234 and the dispatcher will contact another responsible party to take appropriate action.

The City has the right to award this project to the lowest, competent and most responsible bidder.                                                                                                                                                                     


2024-2025 Ravenna/Shepard/Broadway/Richmond Intersection Improvements


City of Twinsburg 

SUM-Ravenna/Shepard/Broadway/Richmond Intersection Improvements, Phase 2, PID 113165

Twinsburg, Glenwillow, Macedonia, Oakwood Village, Ohio

Public Notice and Comment Period 

 

The City of Twinsburg, in partnership with Glenwillow, Macedonia, and Oakwood Village, is planning improvements to the Ravenna/Shepard/Broadway/Richmond Intersection. This federally funded project will improve safety and functionality of the intersection by adding right-turn lanes on Ravenna Road and Broadway Avenue, and a left turn lane on Shepard Road.  The work will also include curb, sidewalk, signal, limited driveway restoration, and drainage improvements.  The proposed project will include the acquisition of minor new permanent and/or temporary rights-of-way as necessary to accommodate the proposed work. 

June 2024  -  Right of Way to be completed

 July 2024 thru end of year

  1. Tree remove of conflicting trees with utility relocation will occur first
  2. Dominion Gas will be relocating a supply line on the NW quadrant of the intersection along Broadway and Shepard Roads.  This line will also connect to a supply line in the NE quadrant of the roadway on the north side of Richmond Road.
  3. Ohio Edison will be relocating poles on the NE side of Ravenna Road and the north side of Shepard Road.   All companion utilities will also relocate to the new poles.

 This project will be bid late fall with construction stating in late winter of 2025.

A minimum of one lane of traffic in each direction for all roads will be maintained during the duration of construction and local access for abutting properties and adjacent streets will be maintained at all times. Construction and lane restrictions will be posted prior to the start of construction. The project is currently in preliminary development and work is anticipated to begin in 2025.  The estimated construction cost of the project is $3,300,000.00.



 

For Further project information go to the City of Twinsburg, and/or Glenwillow, Macedonia, and Oakwood Village websites:

https://mytwinsburg.com/constructionprojects

www.macedonia.oh.us

https://glenwillow-oh.gov/

www.oakwoodvillageoh.com



                                                                                                                                                                  



2024 Road Program 

Construction : April – September. 

Estimate: $1,700,000   

 The work generally includes asphalt resurfacing, asphalt repairs, concrete curb removal & replacement, asphalt grinding,  minor asphalt pavement repairs, curb and sidewalk repairs, catch basin repairs and miscellaneous other repairs.      

Local Street Resurfacing - Full width asphalt grinding, asphalt/concrete pavement repairs, concrete curb & storm basin repairs and asphalt resurfacing. Streets include: Silver Oak Cir, Bellaway Dr, Oakbrook Cir,  Ashcroft Ln, Strauss Ln, and Parker Ln, Laurel Dr, Fairfield Dr , Dutton Dr, Jessica Ct, Melissa Ct, Shepard Trl. Alternates if authorized: Hanford Ln, Merriam Ln, Timberland Ln,  Blossom Ln. The budget for the road program is a fixed amount, it is anticipated that some of the alternates will be awarded, any alternatives not completed this year will be performed as part of 2025 program.

Senior Center Parking Lot Repairs, Neille Lane Pavement Repair – Remove catch basin, replace with type 3A catch basin at curb.  Perform partial depth repairs in areas marked by the Engineer.  Perform double sealcoat and restripe per existing layout.  Mill and overlay repair area on Neille Ln.

Sidewalks and Catch Basins -Saw cutting, removal and replacement of concrete sidewalk, selective tree root pruning at trip hazards and utility adjustments in locations designated on SIDEWALK TABLE.  Catch basin located at 9825 Ravenna Road.  This work can begin in April as weather allows. 

The City has the right to award this project to the lowest, competent and most responsible bidder.                                                                                                                                                                     





2024 Highland Road Resurfacing PID 116479

Construction : July – August

Estimate: $564,000

 Highland Road is a federal classified roadway and eligible for federal funding.  The city received funding through AMATS/ODOT for 90% of the cost to resurface this roadway.  This roadway is also eligible for Permissive Tax fund to provide remaining 10% funding.  The work for this project generally includes asphalt resurfacing, asphalt repairs, concrete curb removal & replacement, asphalt grinding, and minor/major asphalt repairs.   

The City has the right to award this project to the lowest, competent and most responsible bidder.


2024 SR 82 Resurfacing – ODOT PROJECT

Construction : Tentatively 2nd half 2024 

 Estimate: $

 The Ohio Department of Transportation will be resurfacing SR82 from the Ravenna/Cannon intersection to Herrick Drive and continuing East into Twinsburg Township.  This project is part of ODOT’s urban paving program which partners with municipalities to resurface state routes.  The City will be contributing 20% towards the cost of this project.  ODOT will be the lead agency for this project.

The City has the right to award this project to the lowest, competent and most responsible bidder.


 

 

2024 Road Striping Program


 This project consists of re-painting existing traffic lane lines, stop bars, cross walks, lane arrows, and other pavement markings throughout the City, with certain restrictions as denoted herein. Contractor shall not paint over thermoplastic pavement markings on SR 91, SR 82 and a portion of Ravenna Road. The roadway restriping project will begin June 5th and be completed by July 28th. The City has the right to award this project to the lowest, competent and most responsible bidder.