Construction Project Updates

 

 

2021 Road Improvements Project

Amount:  $ 777,766.70
Contractor:  Perrin Asphalt Company
Proposed Construction:
 
April 2021 – Sept 2021

 

Perrin Asphalt has been awarded the project.  This work can begin in April and is scheduled to be completed in September.  This information is currently posted on our website.

The annual road program is a maintenance program providing overlays to extend the life of the pavement.  The following streets are included in this year’s program:

 

Block 1: Sidewalks - Perrin will also be performing miscellaneous sidewalk repairs in the City.  This list is compiled by inspection by the Public Works Dept for utility or other city related failures requiring sidewalk repair. The work included in this project generally consists of saw cutting, removal and replacement of concrete sidewalk, selective tree root pruning at trip hazards and utility adjustments.  This work can begin in April as weather allows.

                                   Sidewalk Locations Map

Block 2:  Catch Basins & Inlets Maintenance – Provide maintenance to existing curb inlets basin at various location listed on CATCH BASIN TABLE and highlighted on Street Index Map.   Work generally includes catch basin reconstruction/ adjustments and parging of structures.  Repair to roadway including, curbs, asphalt, and sidewalk disturbed as part of this project.  This work can begin in April after asphalt plants open up.
                                Catch Basin Repair Location Map

 Block 3:  Davis Way, Darian Lane, Sharon Court, Sterling Court, Windsor Way,  Granby Circle , Ansonia - Full width asphalt grinding, asphalt/concrete pavement repairs, concrete curb & storm basin repairs and asphalt resurfacing. Work should begin in May (OR earlier if Block 1 & 2 complete) and may be completed by July
                                 Street Resurfacing Location Map

 Block 4: Commons Blvd, Merryvale Dr, Lockwood Oval, Pineridge Drive, - Full width asphalt grinding, asphalt/concrete pavement repairs, concrete curb & storm basin repairs and asphalt resurfacing. Work will follow block 3 and should be completed by August

 Block 5: MiscellaneousCoordination with Wheeling and Lake Erie Railroad on paving related to track leveling at railroad at grade crossings in the City as necessary ( SR82 –E. Aurora Road & Cannon Road). Timing shall be coordinated with Railroad.    Misc. Paving repairs City-Wide.

Miscellaneous:At Timothy Lane/Hawkins Lane there will be work on the storm structure at the intersection.  The timing of this has not been firmly established but will most likely occur with Block 3.





2020 Oakwood Drive Improvements Project


Contractor:  Fechko Excavating, LLC
Amount:  $934,069.05
Construction:  March 2020 – August 2020

The work included in this project generally includes replacement of existing sanitary sewer, including service connections with new cleanouts, installation of 8” ductile iron water main, line valves, new hydrant assemblies and water service connections, storm sewer replacement and repairs, new asphalt pavement over cement stabilized sub-grade, concrete aprons and sidewalk repairs, including lawn restoration on Oakwood  Drive. 



2020 Sewer Improvements Project

Proposed Construction:  Delayed to 2021 budget due to COVID-19 impacts

The work included in this project generally consists of maintenance to the City sewer systems.  

Locations:  East Idlewood culvert over a branch of Tinkers Creek; Bissell Drive culvert; Cannon Road between 3130-3264; Sharonbrook Drive; Sunview Drive; Edison Blvd; Independence Pkwy and miscellaneous catch basins & inlets maintenance City-wide.


ODOT PID:  84657  PROJECT  SUM-IR 480-01.36 – Noise walls on I-480 WB in the City of Twinsburg

Contractor:  Shelly and Sands   

Amount of Award:  $3,396,653.15
Construction:  February 2020 – April 2021

Scope of Work:
Construct Concrete Acoustic Noise walls along I-480 between Chamberlin Road and Aurora Road Specifically NSA4B and NSA6A/B. 
This work consists of preparing any necessary shop drawings, and manufacturing, testing, transporting, storing, and installing noise barriers; furnishing and installing drilled shafts; excavating and backfilling; and restoring the work area in accordance with these provisions and in conformity with the dimensions, lines and grades shown on the project plans.

NSA4:  Approx 5,050 foot long barrier constructed along the edge of shoulder of I-480 westbound lane.

NSA6:  Approx 2,000 foot long barrier constructed along the edge of shoulder of I-480 westbound lane and entrance ramp.

Project Schedule:
- Tree and vegetation clearing to start in February, 2020
- Wall construction to start in February, 2021
- 60 day ramp closure will occur in the winter/spring (prior notification and signing required). Detour will be routed to SR91 entrance ramps. Night and weekend construction is anticipated which will include westbound I-480 outside lane closure.



 City-Wide Tree Planting Program

The City-Wide list is being compiled by the Engineering Department and includes new residential developments and replacement trees that have been removed by a City project or as a result of mortality.  Planting for 2020 is postponed due to COVID-19 and will be rescheduled in the future.



SUBDIVISIONS

Quarry Reserve Subdivision

Planning Commission approved a plat for residential subdivision in R-5 district consisting of 27 lots. Quarry Reserve is an extension to the Boulder Brook Development that is across from Miktarian Memorial Parkway.  All roadways have been installed and Pulte Homes is currently building.

Shepard Preserve Subdivision

Residential subdivision consisting of 23 lots. This subdivision connects to Lake Plata Estates and has an entrance off Shepard Road between Ledge Road and Park Ledge Drive.  Coblentz Homes is the builder.

Whispering Woods Phase III

A 30 lot residential development that will continue off the end of Merryvale Drive in Whispering Woods Subdivision. The Plat has been approved by Planning Commission and infrastructure improvements have started.